Highway Development and Planning - IES Previous Year Questions
1. Which one of the following is the chronological sequence in regard to road construction / design / development ?
[IES 1998]
- Telford, Tresaguet, CBR, Macadam
- Tresaguet, Telford, Macadam, CBR
- Macadam, CBR, Tresaguet, Telford
- Tresaguet, Macadam, Telford, CBR
Answer: Option B
Explanation:
The chronological order of road construction is as follows:
Explanation:
The chronological order of road construction is as follows:
- Roman method of design
- Tresaguet method of design
- Metcalf method of design
- Telford method of design
- Macadam method of design
- CBR method of design
- Modified CBR method of design
2.  The length of National Highways as per 3rd 20 year (Lucknow) road plan is given by _____ .
[IES 2000]
- Area of the country/75
- Area of the country/50
- Area of the country/40
- Area of the country/25
Answer: Option B
Explanation:
As per the 3rd 20 year road plan,
Explanation:
As per the 3rd 20 year road plan,
- Total length of road (in km) = Road density x Area of country (in km2) (or) 4.87 x Number of Towns and Villages, whichever is maximum.
- Length of National Highway (in km) = Area of the country (in km2) / 50
- Length of State Highway (in km) = Area of the country (in km2) / 25 (or) 62.5 x number of towns and villages - Area of the country (in km2) / 50, whichever is maximum.
- Length of Major District Roads (in km) = Area of the country (in km2) / 12.5 (or) 90 x number of towns and villages, whichever is maximum.
- Length of Other District Roads and Village Roads = Total length of roads - Sum of lengths of NH, SH and MDR.
3.  In which one of the following location surveys of the road, soil profile sampling is done up to a depth of 1 m to 3 m below the existing ground level ?
[IES 2003]
- Preliminary survey
- Final location survey
- Construction survey
- Material location survey
Answer: Option A
Explanation:
Soil profile sampling is done during the preliminary surveys.
Explanation:
Soil profile sampling is done during the preliminary surveys.
4.  Match List-I (Study) with List-II (Purpose) and select the correct answer using the code given below the lists:
List-I Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â
- Primary road system
- Economic studies
- Engineering studies
- Road use studies
List-II
- Population distribution
- Expressways
- Traffic volume
- Topographic details
[IES 2005]
Codes: A B C D
-  2  1  4  3
-  4  3  2  1
-  2  3  4  1
-  4  1  2  3
Answer: Option A
Explanation:
Explanation:
- Under the 3rd 20 year (Lucknow) road plan, Expressways are classified under the primary road system.
- Population distribution data is collected under economic studies.
- Topographic details are collected during engineering studies.
- Traffic volume is collected by carrying out road use studies.
5.  Under the Nagpur Road Plan, which of the following are NOT relevant in planning the road development programme in a backward district ?
- Existing agriculture drainage network of drain canals.
- Existing number of Panchayat unions.
- Existing length of mud-track roads.
- Number of villages with population of 10000 and above.
[IES 2013]
- 1, 2, 3 and 4
- 1, 2 and 3 only
- 1, 2 and 4 only
- 2, 3 and 4 only
Answer: Option A
Explanation:
The planning of road development programme under Nagpur Road Plan was based on agricultural areas, non-agricultural areas and number of villages with population ranging from 0 to 5000 and more. No details regarding the number of Panchayat unions, mud-track road lengths and agricultural drainage network of drain canals were mentioned.
Explanation:
The planning of road development programme under Nagpur Road Plan was based on agricultural areas, non-agricultural areas and number of villages with population ranging from 0 to 5000 and more. No details regarding the number of Panchayat unions, mud-track road lengths and agricultural drainage network of drain canals were mentioned.